গার্মেন্টস ফ্লোরের জন্য ৪০টি প্রয়োজনীয় সূত্র জেনে রাখুন | Garments Equations - Textile Lab | Textile Learning Blog
গার্মেন্টস ফ্লোরের জন্য  ৪০টি  প্রয়োজনীয় সূত্র জেনে রাখুন
01. Target = 60 ÷ ( SMV x No. of worker x working hour x expected efficiency) .


02. Target = 60÷SMV.


03. Team target =(60÷SMV)x Present operator x Organization efficiency .


04. Target per day = Working hour x 60 x No. of operator / Target SMV.


05. Capacity=Average of total obserb time x 1.66 + 30% Allowance / 60.


06. Factory capacity=No. of operator x working minutes + Present % x average factory efficiency. 


07. Capacity per day = Present operator x working hour x organization efficiency x Attendance. 


08. Weekly capacity = No. of operators x Absenteesm x Clock minutes per week x Average factory efficiency. 


09. Marker efficiency = Area of patterns in the marker / Total area of the marker x 100. 


10. Load = (Contract size x work content) contract 1+ (Contract size x work content) 
Contract 2 + etc. 


11. Load = Order quantity x Work content (SMV of garments). 


12. Observe time = Total cycle time / No. of cycle. 


13. Basic time = Avarage of observe time X Rating %. 


14. Sam = Basic time x Allowance. 


15. Rating = Observe time x Standard rating / Standard rating. 


16. Cycle time = 60 / Team target. 


17. Pitch time = Total SMV / Present operator. 


18. Efficiency = Earn hour / Available hour x 100 


19. Efficiency = SMV / Total time. 


20. Earn hour = (Production x SMV) / 60. 


21. Available hour = Working hour x Use machine(Total manpower) 


22. Performance = (Earn hour / Available hour - Off standard time) x 100. 


23. Improvement = 1-(Production / Capacity). 


24. Balancing efficiency = 1-Balancing loss. 


25. loss pcs = (60/SMV)x Available hours x avg factory effi (61%) -Q.C Pass 


25. Balancing loss = AML-TML/AMLx100. 


26. Standard time = Net operation time x (1+ Ratio of loss time). 


27. Daily output = Working hours (seconds) + Standard time. 


28. Output per operator = Work hours (second) / Total time of operations. 


29. Required No. of operators = Targeted daily output / Daily output per operator. 


30. Target daily capacity = Daily work hours / Standard process time (SPT). 


31. Daily capacity per worker = Daily capacity / No. of workers = Daily Work hours / Standard total processing. 


32. Organization efficiency = Pitch time / Bottle neck process time (x100) = 100/140 x 100 = 71.4% 


33. Upper limit = Pitch time / Target organization efficiency = 100 / 0.85 = 117.6 seconds. 


34. Lower limit = 2 x Pitch time - Upper limit = 2 x 100 - 117.6 = 82.4 seconds. 


35. Planned daily work flow = Daily work hours / Standard process time (SPT) x organization efficiency. 


36. Accumulated avarage time = Daily work hours/AccumulatedxNo.of daysxstandard No.of workers in
the group/No. of pieces produced. 


37. SMV = Basic time + Allowance time + bundle time. 


38. DHU = No. of deffect observe / No. of garments checked. 


39. Booking fabric K.G. = Order quantity / 12 x Fabric consumption per doz. 
40. Garments K.G. = Total receive fabric kg - (Save return kg + Jhute kg + Wastage fabric kg) 


41. Input to sewing pcs. = Total in pcs - (Print Embroidery short & wastage + Cutting wastage pcs.) 


39. Fabric consumption (CM) = Length x chest x 2 x GSM / 1000 / 10000 x 12 + Wastage%. 

40. Fabric consumption (Inch) = Length x chest x 2 x GSM / 1000 / 1550 x 12 + Wastage%.

গার্মেন্টস ফ্লোরের জন্য ৪০টি প্রয়োজনীয় সূত্র জেনে রাখুন | Garments Equations

গার্মেন্টস ফ্লোরের জন্য  ৪০টি  প্রয়োজনীয় সূত্র জেনে রাখুন
01. Target = 60 ÷ ( SMV x No. of worker x working hour x expected efficiency) .


02. Target = 60÷SMV.


03. Team target =(60÷SMV)x Present operator x Organization efficiency .


04. Target per day = Working hour x 60 x No. of operator / Target SMV.


05. Capacity=Average of total obserb time x 1.66 + 30% Allowance / 60.


06. Factory capacity=No. of operator x working minutes + Present % x average factory efficiency. 


07. Capacity per day = Present operator x working hour x organization efficiency x Attendance. 


08. Weekly capacity = No. of operators x Absenteesm x Clock minutes per week x Average factory efficiency. 


09. Marker efficiency = Area of patterns in the marker / Total area of the marker x 100. 


10. Load = (Contract size x work content) contract 1+ (Contract size x work content) 
Contract 2 + etc. 


11. Load = Order quantity x Work content (SMV of garments). 


12. Observe time = Total cycle time / No. of cycle. 


13. Basic time = Avarage of observe time X Rating %. 


14. Sam = Basic time x Allowance. 


15. Rating = Observe time x Standard rating / Standard rating. 


16. Cycle time = 60 / Team target. 


17. Pitch time = Total SMV / Present operator. 


18. Efficiency = Earn hour / Available hour x 100 


19. Efficiency = SMV / Total time. 


20. Earn hour = (Production x SMV) / 60. 


21. Available hour = Working hour x Use machine(Total manpower) 


22. Performance = (Earn hour / Available hour - Off standard time) x 100. 


23. Improvement = 1-(Production / Capacity). 


24. Balancing efficiency = 1-Balancing loss. 


25. loss pcs = (60/SMV)x Available hours x avg factory effi (61%) -Q.C Pass 


25. Balancing loss = AML-TML/AMLx100. 


26. Standard time = Net operation time x (1+ Ratio of loss time). 


27. Daily output = Working hours (seconds) + Standard time. 


28. Output per operator = Work hours (second) / Total time of operations. 


29. Required No. of operators = Targeted daily output / Daily output per operator. 


30. Target daily capacity = Daily work hours / Standard process time (SPT). 


31. Daily capacity per worker = Daily capacity / No. of workers = Daily Work hours / Standard total processing. 


32. Organization efficiency = Pitch time / Bottle neck process time (x100) = 100/140 x 100 = 71.4% 


33. Upper limit = Pitch time / Target organization efficiency = 100 / 0.85 = 117.6 seconds. 


34. Lower limit = 2 x Pitch time - Upper limit = 2 x 100 - 117.6 = 82.4 seconds. 


35. Planned daily work flow = Daily work hours / Standard process time (SPT) x organization efficiency. 


36. Accumulated avarage time = Daily work hours/AccumulatedxNo.of daysxstandard No.of workers in
the group/No. of pieces produced. 


37. SMV = Basic time + Allowance time + bundle time. 


38. DHU = No. of deffect observe / No. of garments checked. 


39. Booking fabric K.G. = Order quantity / 12 x Fabric consumption per doz. 
40. Garments K.G. = Total receive fabric kg - (Save return kg + Jhute kg + Wastage fabric kg) 


41. Input to sewing pcs. = Total in pcs - (Print Embroidery short & wastage + Cutting wastage pcs.) 


39. Fabric consumption (CM) = Length x chest x 2 x GSM / 1000 / 10000 x 12 + Wastage%. 

40. Fabric consumption (Inch) = Length x chest x 2 x GSM / 1000 / 1550 x 12 + Wastage%.

৩টি মন্তব্য:

নামহীন বালক বলেছেন...

আই সম্পর্কে আরে বেশি কিছু লিখলে ভালো হতো

Unknown বলেছেন...

Boss consumption সম্পর্কে আরও বিস্তারিত আলোচনা করেন বস

Unknown বলেছেন...

কনজামশন সম্পর্কে বিস্তারিত আলোচনা করুন বস ফেব্রিক প্লাস বডি সব কি এক নাকি প্র্যাকটিক্যাল সংঘাতে দেখা দিয়েন কারিকুলাম ভাবে বস